METHODS FOR IMPLEMENTING IRRIGATION CHANNELS

IMPLEMENTING IRRIGATION CHANNELS METHODS
This method of implementation is made as a condition to fulfill the technical administration of the auction with the intention that in assessing whether the service provider can carry out the work to be carried out.IMPLEMENTING IRRIGATION CHANNELS METHODS
Implementation Method is a work plan that is used as a reference in carrying out the work of a construction project. The implementation method includes grouping activities based on activities, time allocation and work methods for the main jobs. The basic considerations used in carrying out construction work are the realization of buildings in accordance with planning with consideration of the effectiveness of time and cost efficiency.IMPLEMENTING IRRIGATION CHANNELS METHODS
 This Implementation Method contains descriptions of the contractor's strategy from pre-employment to post-work (maintenance period), to carry out work to fit the planning drawings, requirements and finish on time in accordance with the contract.IMPLEMENTING IRRIGATION CHANNELS METHODS

A. PRA IMPLEMENTATION WORK:
Before the implementation begins, the contractor will prepare itself, set the strategy to carry out the work, both in terms of technical and financial aspects. The steps for the contractor to take include:
- Make a working time plan: Time Schedule
- Prepare personnel
- Prepare equipment
- Preparing Flow Cash
-        etc.
Time schedule and curve "S" are made rationally between work with one another. In this time schedule, the work weight is divided by time requirements so that we can monitor each time the work exceeds or is too late for the time we planned.IMPLEMENTING IRRIGATION CHANNELS METHODS

  I. PREPARATION JOB
a. Measuring / Uitzet
In the construction of irrigation networks in. ciburuluk (32 ha) carried out measurements or uitzet at the location of the measurement work carried out including measuring the dimensions of the length, width and height of irrigation this measurement was carried out using a meter, theodolite, and whaterpass so that the maximum results of measurements were made referring to working drawings.
b. Kisdam or Drying Works IMPLEMENTING IRRIGATION CHANNELS METHODS
In the construction of irrigation networks in. Ciburuluk (32 ha) is carried out by kdamdam or land drying by using a water pump or alcon drying work aimed at facilitating masonry work and other work.
c. Project Nameplate Jobs
On irrigation network work in. Ciburuluk (32 ha) carried out project nameplate building work, the project nameplate aims to inform work activities to the general public.IMPLEMENTING IRRIGATION CHANNELS METHODS

d. Documentation and Reporting
Documentation and Reporting on irrigation network work in. Ciburuluk (32 ha) is carried out in the form of taking photos and making daily, weekly and monthly reports during the work process IMPLEMENTING IRRIGATION CHANNELS METHODS

II. JOB BUILDING (NEW) WORK
a. Rocky Land Excavation
Rocky Excavation is excavation of soil containing loose rock by using human power or heavy equipment such as PC 100 / PC 200 Excavators (depending on needs). The service provider must carry out this excavation by following the plan drawing.
Implementation Method
Ø Excavation of rocky land which cannot be used as fill material must be disposed outside the work area
Ø Material from the excavation that will be used as waste material must be approved by the directors.
Ø Any material that is excessive for the needs of the material must be paid by the service provider to the location specified by the board of directors.
Ø The Service Provider must be responsible for all arrangements, obtaining permits for the disposal of material from the land owner where the disposal is carried out.
Ø Service providers in carrying out excavation work must be tried to be quite safe from landslides, especially at the place of heavy equipment.
Ø If the work is completed, the service provider must notify the directors for inspection.
IMPLEMENTING IRRIGATION CHANNELS METHODS
Planned time: On Schedule
Tools used: Hoes, Masonry Tools, Excavators etc.
Labor requirements: 10 Workers
Material to be used: Soil.
IMPLEMENTING IRRIGATION CHANNELS METHODS
b. Pair of Kali / Gunung Batu 1: 4
Stone Couple work is a stone / mountain pair work using a cement cement mixture formed in accordance with the Implementation drawing IMPLEMENTING IRRIGATION CHANNELS METHODS
How to do it:
Ø The stone used must be clean and hard stone and has been approved by the Board of Directors.
Ø The sand used must be good and has been approved by the Board of Directors.
Ø Species / mortification of masonry work must be from a mixture of cement and sand with a volume ratio of 1 pc: 4 psr using a concrete mixer
Ø The pair of stones must be arranged in such a way that between the rock and the rock is processed homogeneously, so that the stones do not coincide / touch. The renen stone (face stone) must have a distance (nat width between 1-2 cm)


c. Plastering 1; 4
Plastering is a job IMPLEMENTING IRRIGATION CHANNELS METHODS